23-7366 10 Browning street Recladding - Public Project Site
-
05th December 2024, Before the weekend
Before the weekend can all trades please ensure general waste is disposed of an all spoil is loaded out or consolidated.
pits and trenches need also to be filled or barricaded for safety to others. -
22nd March 2024, Good Morning and Welcome to Browning Street Re Clad Project BEWARE OF PUBLIC INTERACTION BEWARE OF LIVE TRAFFIC AND MOVEMENTS
BEWARE OF INCLEMENT WEATHER WORK TO CONDITIONS
Works Today -
TCI - Set up and maintain carpark lane closure to Entrance,Exist and Ramp EWP and ropes Works
Access Scaffolding - Scaffold removal to North and West Wall Corner South Building
Kaybre Painting - Start Painting Blade Sign and Bulkheads to undercroft area
Glenview Developments - Continue Bulkhead works and South Foyer
QS Cladding - EWP Works to East Face Carpark top area and ramp
Continue Panel works East face North Building
Continue Caulking Works
Continue works to Bottle O Signage
Safety-
MAKE SURE YOU FOLLOW YOUR SWMS
Set up work zones signage if required barricade with bollard and flagging or water barriers
Roof and Ropes works - Ensure you are harnessed and attached to either rope access or harness and fall restraint too static line if you are working closer then 2m from an live edge
Drilling overhead - Ensure you adapt Double protection either face shield or goggles
Live Traffic - beware of live traffic and movement, delineate work area,
Follow and adhere to your SWMS
Pedestrian interaction - beware of public interaction , set up and maintain exclusion zones, correct use of spotters, positive communication between all parties
Plant and People - Prestart plant and machinery before works are started, Ticketed compliment operators only, positive communication between plant and people visual and verbal, delineate work area
Uneven Surfaces - Eyes on path , mind on task, ensure secure footing when working in and around site
House Keeping - Maintain good house keeping , tidy up as you go along,ensure you allow enough time at the end of each shift to tidy properly
Manual Handling - Correct posture and lift technique, team lifts or mechanical aid, when performing a team lift ensure clear and positive communication is used
Dehydration - Fluids regularly , sunblock available, shade breaks if required , look out for your mates -
29th January 2023, machinery
Please make sure you look for machinery working in between buildings prior to access please
Current Site Weather
Last Updated at: 5:21 PM
Temperature: 28C (App 32C)
Wind Speed: 4KMH
Max. Wind: 13KMH @1:21 PM
Rain since 9AM: 0.2mm
Min Temp: 24C @5:38 AM
Max Temp: 32C @11:54 AM
Gust: 6KMH
Max Gust: 15KMH @3:21 PM
Observation Location - Brisbane, QUEENSLAND
Time Zone - Australian Eastern Standard Time
Forecast - Sunday, 11 January
Showers.
Min: 23C Max: 26C
Chance of Rain: 90%
Expected Rainfall: 5 to 35mm
Forecast Location - Brisbane, QUEENSLAND
Time Zone - Australian Eastern Standard Time
Tomorrow - Monday, 12 January
Showers.
Min: 22C Max: 29C
Chance of Rain: 80%
Expected Rainfall: 0 to 15mm
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Complete your site registration online at your convenience and save yourself time.
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Complete your site registration online at your convenience and save yourself time.